N C C RTU Upgrade in KM Primary Substations

Year2023
ValueUS$ 2.0 M
Scope

✓ ICA Works

Project Overview

Contract is intended to upgrade the NCC Microsol RTU Xcell processor installed in Kahramaa Primary Substations (22 Nos  of Substations  Approx).  The  Contract  shall also  cover hardware/software upgrade, replacement of Cell Processor modules. The proposed up-gradation is to improve the System performance and to have additional system features.

SCOPE OF WORK

• Upgrading of NCC Microsol Xcell processor Modules to the latest version in Kahramaa Primary Substations.

• Upgrading the Processor Modules (CPR031 to latest Microsol CPR0XX available hardware without any Major modification in Wiring and existing Functionality).

• Software and Firmware Upgrade of Microsol XCell Base Software and I/O Cards as applicable.

Project Start Date: Sep 2021

Completion Date: Sep 2023

 