Home / Project Detail
| Year | 2023 |
| Value | US$ 1.9 M |
| Scope | ✓ Instrumentation Works |
SCOPE OF WORK
Supply, replacement, Testing (including Stability test) & commissioning of 12 nos. of existing 220kV feeder protection relays including dual FO connection for 220kV RASLAFFAN (NEW SCS)-RASLAFFAN POWER STATION (Schneider SCS) feeders 1,2&3, which are having GE/Alstom/Areva Relays at present. Main-1 shall be GE/Schneider make and Main-2 shall be Siemens/ABB make 87C Relays.
Project Start Date: Sep 2021
Completion Date: Sep 2023
Sunday – Thursday
8:00 AM to 5:30 PM
Friday & Saturday
Closed